MORD 242015AI Search Enabled✦ AI Generated

MORD 24 — Do It Yourself Construction of Cement Stabilized Sub Base/Base

MORD 24 (2015) provides comprehensive guidelines for the do-it-yourself construction of cement stabilized sub-base and base layers for rural roads in India. It covers material selection, mix design, construction operations, quality control, and durability considerations specifically tailored for low-volume traffic and challenging environmental conditions. This standard is essential for engineers and contractors involved in cost-effective, durable pavement construction using locally available materials stabilized with cement.

8Sections
64Clauses Indexed
✓AI Search Ready
2015Edition
Roads and Bridges IRC- Indian road congress Category
Alternative search terms: MORD 24 PDF, MORD 24 pdf free download, MORD 24 free download pdf, MORD24 PDF, MORD-24 PDF, MORD 24 2015 PDF, MORD 24:2015 PDF, MORD 24-2015 PDF, MORD 24 (2015) PDF, MORD 24 2015 edition PDF, MORD 24 edition 2015 PDF

What This Standard Covers

MORD 24 (2015) provides comprehensive guidelines for the do-it-yourself construction of cement stabilized sub-base and base layers for rural roads in India. It covers material selection, mix design, construction operations, quality control, and durability considerations specifically tailored for low-volume traffic and challenging environmental conditions. This standard is essential for engineers and contractors involved in cost-effective, durable pavement construction using locally available materials stabilized with cement.

Who Uses This Standard

  • Rural Road Engineers
  • Pavement Designers
  • Construction Supervisors
  • Quality Control Inspectors
  • Contractors for Rural Infrastructure
  • Materials Testing Laboratories
  • Government Road Development Agencies

Key Topics Covered

✓Material selection and gradation requirements for cement stabilization
✓Mix-in-place stabilization techniques
✓Design criteria for cement stabilized sub-base and base layers
✓Quality assurance and control tests during construction
✓Moisture content control and measurement methods
✓Cracking causes and control in stabilized layers
✓Construction operations including spreading, mixing, compaction, and curing
✓Durability issues and prevention of surface disintegration
✓Methods to control reflective cracking
✓Analysis of rates and cost considerations
✓Handling and storage of cement stabilizers
✓Use of local materials and industrial wastes for stabilization

Table of Contents

1Introduction▼

Introduction - MORD 24 Key Points

Purpose:

  • Guide for rural road development by National Rural Roads Development Agency (MoRD).

Scope:

  • Covers selection, specifications, construction, design, quality assurance, and precautions for stabilized materials in rural roads.

Key Specifications for Soil-Cement Base (Clause 6.2)

  • Minimum 7-day unconfined compressive strength: 3 MPa (laboratory test)
  • Minimum thickness: 100 mm (as per pavement design catalogue)
  • Soil preparation: Thorough pulverization and mixing (Clause 404 MoRD)
  • Clayey soils: May require lime pre-treatment before cement stabilization

Pavement Design Catalogue for Cement Treated Bases (Excerpt)

Traffic Category (Cumulative ESAL)Subgrade CBRThickness (mm) Range*
T1 (10,000 - 30,000)5-6 (Fair)100 - 125
T4 (100,000 - 200,000)3-4 (Poor)100 - 125
T7 (600,000 - 1,000,000)7-9 (Good)75 - 140
T9 (1,500,000 - 2,000,000)10-15 (Very Good)75 - 125

*Exact thickness depends on detailed design and subgrade strength.


Summary Diagram (Pavement Layer)

graph TD
  A[Surface Dressing] --> B[Bituminous Macadam]
  B --> C[Crack Relief Aggregate Layer]
  C --> D[Cement Treated Base]
  D --> E[Cement Treated Subbase]
  E --> F[Subgrade Soil]

References:

  • Clause 6.2, MORD 24
  • IRC:SP:72-2015 Pavement Design Catalogues
  • MoRD Specifications Clause 404
2Selection of Stabilizer▼

Selection of Stabilizer (MORD 24, Clause 2.0)

The choice depends on plasticity index (PI) and particle size distribution (% passing 0.075 mm sieve):

Stabilized MaterialSoil PropertiesMore than 25% passing 0.075 mmLess than 25% passing 0.075 mm
PI < 1010 < PI < 20PI > 20
CementYesYes*
Lime-YesYes
Lime-PozzolanaYes-No
  • PI = Plasticity Index, PP = Plasticity Percentage
  • Coefficient of Uniformity (Cu) should be ≥ 5, preferably > 10 for cost-effective stabilization.
  • High plasticity soils with clay minerals are better stabilized with lime.
  • Cement requires pre-treatment with ~2% lime for high plasticity soils.

Storage & Handling (Clause 7.4)

Age% Strength Reduction in Cement
After 3 months20%
After 6 months30%
After 1 year40%
After 2 years50%

Summary:

  • Use lime for high PI soils (>20).
  • Use cement for low PI soils and well-graded materials.
  • Use lime-pozzolana for intermediate conditions.
  • Ensure stabilizer storage to minimize strength loss.
flowchart TD
    A[Soil Sample] --> B{Passing 0.075 mm > 25%?}
    B -- Yes --> C{PI < 10?}
    C -- Yes --> D[Cement or Lime-Pozzolana]
    C -- No --> E{PI 10-20?}
    E -- Yes --> F[Lime or Cement]
    E -- No --> G[Lime]
3Specifications and Test Requirements for Stabilized Materials▼

Specifications and Test Requirements for Stabilized Materials (MORD 24 - Clause 3.0 & 3.1)

  • Material Quality:

    • Gradation and soil/granular type critically affect pavement performance.
    • Materials must meet minimum quality standards to reduce carbonation and cracking risks.
  • Strength Evaluation Tests:

    • Unconfined Compressive Strength (UCS): Measures compressive strength without lateral confinement.
    • California Bearing Ratio (CBR): Assesses bearing capacity of stabilized materials.

Key Test Formulae:

  • Unconfined Compressive Strength (UCS):
    [ UCS = \frac{P}{A} ]
    Where:

    • (P) = Maximum load at failure (N)
    • (A) = Cross-sectional area (mm²)
  • California Bearing Ratio (CBR):
    [ CBR(%) = \frac{P_{test}}{P_{standard}} \times 100 ]
    Where:

    • (P_{test}) = Load on soil sample at 2.5 mm penetration
    • (P_{standard}) = Load on standard crushed stone at 2.5 mm penetration

Typical Specifications (Summary):

ParameterRequirement
GradationWell-graded, free from deleterious materials
UCSGenerally > 1.5 MPa after curing
CBRMinimum 80% for base layers
Additive ContentAs per soil type and test results

flowchart TD
    A[Soil/Granular Material] --> B{Meets Spec?}
    B -- Yes --> C[Stabilize with Standard Additive]
    B -- No --> D[Increase Additive Content]
    C --> E[Perform UCS & CBR Tests]
    D --> E
    E --> F{Strength OK?}
    F -- Yes --> G[Use in Pavement]
    F -- No --> H[Modify Mix or Material]

Note: More additive may be needed if material quality is poor, increasing cracking risk. Always verify with UCS and CBR tests before construction.

4Construction Operations▼

Construction Operations (MORD 24 - Clause 4.0 & Table 8)

Key quality control tests during construction ensure proper soil stabilization and compaction:

Test TypeFrequency & Notes
Pulverization of Soil ClodsAt least 3 tests daily, spread over the day's work.
Placement Moisture ContentPer IS:2720 Part 2; 3 tests daily, same frequency as pulverization.
In-situ Density MeasurementsPer IS:2720 Part 28; 3 tests daily. <br> - Average ≥ specified compaction degree.<br> - Individual values ≥ 99% of specified compaction.
Thickness of Compacted LayerChecked randomly during construction.

Important Specifications:

  • Degree of Compaction: Achieve at least the specified compaction (usually ≥ 95% of Modified Proctor).
  • Moisture Content: Maintain optimum moisture for maximum compaction efficiency.
  • Layer Thickness: Follow design thickness, typically 150-200 mm per layer for stabilized sub-base/base.
flowchart LR
    A[Start Construction] --> B[Soil Pulverization Test (≥3/day)]
    B --> C[Check Moisture Content (≥3/day)]
    C --> D[Compact Soil Layer]
    D --> E[Density Test (≥3/day)]
    E --> F{Compaction ≥ Specified?}
    F -- Yes --> G[Check Thickness Randomly]
    F -- No --> H[Rework Layer]
    G --> I[Proceed to Next Layer]
    H --> D

This process ensures quality stabilized pavement layers per MORD guidelines.

5Analysis of Rates▼

Analysis of Rates for Cement Treated Soil Sub-base/Base Course (MORD 24)

Based on Clause 5.0 and Clause 4.6 of MORD 24 and IRC Standard Data (2014), key points are:

Key Specifications:

  • Item: Cement Treated Soil Sub-base/Base Course
  • Reference: Sl no. 4.6, MORD Standard Data Book (IRC, 2014)
  • Purpose: To arrive at unit rates for construction items considering material, labor, and equipment costs.

Typical Components in Analysis of Rates:

ComponentDescription
Material CostCement, soil, water
Labor CostSkilled and unskilled labor for mixing, spreading, compacting
Equipment CostCost of mixers, compactors, transport
Overheads & ProfitContractor’s overheads and profit margin

Formula for Unit Rate:

[ \text{Unit Rate} = \frac{\text{Total Cost of Materials + Labor + Equipment + Overheads}}{\text{Quantity of work (e.g., m}^3\text{ or m}^2\text{)}} ]

Example Table Extract (Indicative):

Item DescriptionQuantityUnitRate (₹)Amount (₹)
Cement (43 Grade)50kg6.5325
Soil (Excavation & Preparation)1m³150150
Labor (Mixing, Spreading, Compacting)3man-hr100300
Equipment (Mixer, Compactor)1hr200200
Total975

Summary:

  • Refer Clause 5.0 for methodology.
  • Use Sl no. 4.6 in MORD Standard Data Book for detailed unit rates.
  • Include all cost components: materials, labor, equipment, overheads.
  • Adjust rates as per local market conditions.
flowchart LR
    A[Material Cost] --> D
6Designs of Cement Stabilised Sub Base and Base▼

Design of Cement Stabilised Sub Base and Base (MORD 24)

Key Specifications

  • Material Gradation (Table 5):
IS Sieve (mm)% Passing (Sub-base/Base)
53.0100
37.595 - 100
19.045 - 100
9.535 - 100
4.7525 - 100
0.68 - 65
0.35 - 40
0.0750 - 10
  • Material Properties (Table 4):
PropertyLimit
Liquid Limit (%)< 45
Plasticity Index (%)< 20
Organic Content (%)< 2
Total SO4 Content (%)≤ 0.2
Water Absorption (Coarse Agg.)< 2% (if >2%, conduct soundness test as per IS 383)
Minimum Cement Content (%)≥ 5

Design Guidelines

  • Use IRC SP-72 (2015) design charts for thickness based on subgrade CBR and traffic.
  • Cement content should ensure adequate strength and durability.
  • Grading must provide a well-closed surface finish with Cu ≥ 5.
  • Plastic fines passing 425 micron should meet liquid limit and plasticity index limits.
  • Thickness and grading choice depend on pavement design and Engineer-in-Charge approval.

Typical Design Flow (Simplified)

flowchart TD
    A[Determine Subgrade CBR] --> B[Select Traffic Category]
    B --> C[Use IRC SP-72 Design Charts]
    C --> D[Determine Thickness of Cement Stabilised Layer]
    D --> E[Check Material Gradation & Properties]
    E --> F[Select Cement Content & Mix Design]
    F --> G[Construction & Quality Control]

Summary: Follow grading limits, material specs, and IRC SP-72 charts to design cement stabilized sub-base/base layers ensuring durability and strength.

7Quality Assurance▼

Quality Assurance in MORD 24 (Clause 7.0 & 7.3.1.2)

Key quality control tests during construction for stabilized materials as per Table 8:

Test TypeFrequency & Specification
Pulverization of Soil ClodsMinimum 3 tests daily, spread throughout the day's work.
Placement Moisture ContentPer IS:2720 Part 2, minimum 3 tests daily, spread over the day.
In-situ Density MeasurementsPer IS:2720 Part 28, minimum 3 tests daily; <br>- Average ≥ specified degree of compaction <br>- Individual test values ≥ (specified degree of compaction - 1%)
Thickness of Compacted LayerRandom checks during construction.

Important Notes:

  • The degree of compaction is critical for ensuring soil stability.
  • Moisture content must be controlled to achieve desired compaction.
  • Thickness checks ensure uniform layer compaction.
flowchart TD
    A[Start Construction] --> B[Pulverization Tests (3/day)]
    B --> C[Moisture Content Tests (3/day)]
    C --> D[In-situ Density Tests (3/day)]
    D --> E{Check Degree of Compaction}
    E -->|Average ≥ Specified| F[Accept Layer]
    E -->|Average < Specified| G[Rework Layer]
    F --> H[Thickness Check (Random)]
    G --> B

This ensures consistent quality and compliance with MORD 24 standards.

8Precautions to be taken while using Stabilized Materials▼

Precautions while using Stabilized Materials (IS Code MORD 24, Clause 8.0):

  • Moisture Control: Maintain optimum moisture content during mixing and compaction to achieve desired strength.
  • Mixing Uniformity: Ensure thorough and uniform mixing of stabilizing agents (lime, cement, bitumen) with soil.
  • Curing: Provide adequate curing (minimum 7 days for cement/lime stabilization) to develop strength.
  • Compaction: Achieve specified compaction (typically 95% Proctor density) to reduce voids and increase durability.
  • Avoid Contamination: Prevent contamination by organic matter or salts which reduce stabilization effectiveness.
  • Temperature Control: For bituminous stabilization, maintain temperature within recommended limits to avoid premature setting or poor bonding.

Specifications and Test Requirements (Clause 3.0):

PropertyTest MethodTypical Requirement
Moisture ContentIS 2720 (Part 2)Optimum moisture for compaction
Maximum Dry DensityIS 2720 (Part 8)As per Proctor test results
Unconfined Compressive StrengthIS 2720 (Part 10)Minimum 1.5 MPa after 7 days curing
Plasticity IndexIS 2720 (Part 5)Should be reduced after stabilization
Durability (Wet-Dry)IS 4332Loss in strength < 20%

Summary:

  • Use optimum moisture and uniform mixing.
  • Ensure proper compaction and curing.
  • Test for strength, moisture, density, and durability per IS standards.
  • Avoid contamination and control temperature during mixing and curing.
flowchart TD
    A[Soil Sampling] --> B[Testing for Properties]
    B --> C{Is Soil Suitable?}
    C -- Yes --> D[Add Stabilizer]
    D --> E[Mix Uniformly]
    E --> F[Control Moisture]
    F --> G[Compaction]
    G --> H[Curing]
    H --> I[Strength Testing]
    I --> J{Meets Specs?}
    J -- Yes --> K[Use in Construction]
    J -- No --> L[Adjust Mix

Popular Questions About MORD 24

?What are the suitable soil and aggregate types for cement stabilization under this standard?▼

Suitable Soil and Aggregate Types for Cement Stabilization (MORD 24)

  • Soil Types:

    • Well-graded aggregates with sufficient fines to fill voids and support coarse particles.
    • Sandy materials with Plasticity Index (PI) < 30.
    • Fine-grained soils with >50% passing 75 µm sieve, having PI < 20 and Liquid Limit (LL) < 40.
    • For subgrade improvement, soils with LL < 45, PI < 20, and organic content < 2%.
    • Total sulfate content must be below 0.2% to avoid sulfate attack.
  • Aggregate Types:

    • Granular materials and silty cohesive soils are preferred.
    • Clayey soils are better stabilized with lime rather than cement.
    • Degree of pulverization should be > 60% for effective mixing.
  • Cement Content:

    • Typically 2-3% for cement-modified soil (CBR > 25).
    • Up to 7-10% for soil-cement with compressive strength > 20 kg/cm².
    • Minimum cement content for subgrade stabilization: 2% (can be reduced to 0.5% with advanced equipment and lab verification).

Summary Table (from Clause 3.2.1)

PropertyValue
Liquid Limit (LL)< 45%
Plasticity Index (PI)< 20
Organic Content< 2%
Total SO4 Content< 0.2%
Minimum CBR≥ 15%
Minimum Cement Content2% (min)
Degree of Pulverisation> 60%
Mixing Temperature> 100°C

Note: Proper mixing and pulverization are critical for uniform cement-soil bonding and strength development.

?How is the correct cement content and moisture level determined for stabilization?▼

To determine correct cement content and moisture level for soil stabilization as per MORD 24:

Cement Content

  • Cement-modified soil: 2-3% cement increases CBR > 25 (used for sub-base/base).
  • Soil-cement: 7-10% cement yields 7-day UCS ≥ 20 kg/cm² (hard mass).
  • Cement content depends on soil gradation and fines content; more fines require careful adjustment.

Moisture Content

  • Moisture must be adequate for hydration and workability.
  • Optimum moisture is near the soil’s optimum moisture content (OMC) from Proctor tests, ensuring intimate mixing.
  • Moisture too low → incomplete hydration; too high → weak strength and compaction issues.

Procedure (Clause 7.2)

  • Conduct laboratory tests (UCS, CBR) to estimate cement and moisture.
  • Perform a preliminary field trial at least 10 days before main work to finalize mix proportions, moisture, and compaction methods.

Key Factors (Clause 1.4)

  • Soil type, cement quantity, water quantity, mixing, compaction, curing.
  • Use well-graded soils with fines for better cement bonding.

Summary Table

ParameterTypical Range/Value
Cement Content2-3% (modified), 7-10% (soil-cement)
Moisture ContentNear Optimum Moisture Content (OMC)
Plasticity Index< 30 (sandy), < 20 (fines >50%)
Liquid Limit< 40 (for fine-grained soils)

Loading diagram…

This iterative approach ensures optimized cement and moisture for durable soil stabilization.

?What quality control tests are required during construction to ensure durability?▼

Quality Control Tests for Durability (MORD 24, Clause 7.3)

To ensure durability during construction of stabilized layers, the following QC tests are mandated:

Before Construction (Table 7)

TestFrequency
Cement quality & Lime purity (IS:1514)One test per lot
Unconfined Compressive Strength (IS:4332 Part 5)One test on 3 specimens per 1 km length

During Construction (Table 8)

TestFrequencyRequirement
Pulverization of soil clods≥ 3 tests daily, spread over the dayEnsure adequate soil breakdown
Placement Moisture Content (IS:2720 Part 2)≥ 3 tests dailyMaintain optimum moisture for compaction
In-situ Density (IS:2720 Part 28)≥ 3 tests dailyAverage ≥ specified compaction; no individual < 1% below specified
Thickness of compacted layerRandom checksConfirm layer thickness meets design

Additional Notes

  • Sampling should be representative, e.g., along diagonals of the area.
  • Mix uniformity must be visually inspected by trenching for color consistency.
  • Frequent checks on mixing efficiency and moisture ensure design objectives and durability.
Loading diagram…

Summary: Regular, frequent testing of material properties and compaction parameters per IS codes ensures durability of stabilized layers.

?How can cracking in cement stabilized layers be minimized or controlled?▼

To minimize/control cracking in cement stabilized layers (per IS MORD 24):

Key Causes:

  • Drying shrinkage (soil type, cement %, compaction, curing)
  • Temperature/moisture changes
  • Subgrade restraint and traffic loads

Control Measures:

  1. Proper Construction & Curing:

    • Ensure uniform compaction and curing to reduce shrinkage.
    • Lay material in moderate temperatures to reduce thermal shrinkage.
  2. Pre-cracking Technique:

    • Apply multiple passes of a vibratory roller 1-2 days after compaction.
    • Induces micro-cracks that relieve shrinkage stresses, preventing wide cracks.
    • Micro-cracks heal over time without reducing strength.
  3. Stress Relief Layers:

    • Use flexible interlayers to reduce stress transfer:
      • Bituminous surface treatment (chip seal)
      • Geotextile fabric between base and asphalt
      • 50-100 mm unbound granular layer ("sandwich" layer)
  4. Material Selection:

    • Avoid very high cement content that causes wide cracks.
    • Consider additives to modify cement hardening and reduce early strength.

Summary Table:

MethodPurposeEffect
Proper curingReduce shrinkageFewer cracks
Pre-crackingInduce micro-cracksMinimize wide cracks
Flexible interlayersStress relief at interfacePrevent reflection cracks
Cement content controlControl shrinkage & strengthNarrower crack patterns

Loading diagram…

Note: Reflection cracks < 3 mm are generally non-detrimental; wider cracks require intervention.

?What construction methods are recommended for remote or low-resource settings?▼

For remote or low-resource settings, IS code MORD 24 recommends Mix-in-Place Stabilization for rural roads, due to its simplicity and minimal equipment needs.

Key Construction Methods:

  • Mix-in-Place Stabilization:
    • Stabilizer (cement/lime) is spread on the in-situ soil.
    • Soil and stabilizer are mixed using adapted agricultural or simple machinery.
    • Suitable for thickness ≤ 200 mm and low traffic volume roads.
    • Requires proper compaction and curing.

Recommended Equipment:

  • Road grader (with ripper) for loosening and leveling.
  • Rotavator or adapted machinery for mixing soil and stabilizer.
  • Grid roller to break oversized aggregates.
  • Water bowser with controlled sprinklers for uniform moisture.
  • Compactors (6-12 tons static or vibratory rollers) for required compaction.
  • Labour for manual tasks like spreading cement, removing stones, and finishing.

Advantages:

  • Economical, uses local materials.
  • Minimal heavy machinery needed.
  • Adaptable to remote areas.
Loading diagram…

This approach balances cost, logistics, and durability for rural road construction in challenging environments.

✦

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in MORD 24. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required